Refurbishment of injection solution conditioning
Information about project
| Investor: | HBM Pharma, s.r.o. |
| Construction site: | HBM Pharma, s.r.o., Martin, Slovak Republic |
| Customer: | HBM Pharma, s.r.o. |
| Scope of works: | Construction study and documentation. |
| PD development: | 2008 |
| Execution: | 2009 |
| Investment costs: | approx. CZK 10.0 million |
The company designed the injection solution conditioning in 1994, predominantly in class “D” cleanness to EU GMP (class 8 to ISO 14644–1). The refurbishment of the space helped enhance the cleanness class to “C” to EU GMP (class 7 to ISO 14644–1) in order to introduce aseptic pharmaceutical form production.
Technical data on the construction:
Out of the original 700 m² of class “D” space, 470 m² was upgraded to
class “C” and 40 m² to class “C/D”.